Care Home Development, Hatton, Derby

Project Snapshot

  • Project: New-build care home

  • Location: Hatton, Derbyshire

  • Client: Care home developer

  • Services: Electricity and water (temporary and permanent supplies)

  • Scope: Strategy, coordination, and delivery

Key Outcomes:

  • HV solution redesigned three times without programme delay

  • Temporary power delivered without reliance on generators

  • 140kW solar PV approved via G99

  • Commercial risks mitigated through proactive negotiation

Development & Electrical Load Profile

The development comprised a 66-bed, 24-hour care facility with a significant and varied electrical demand.

Key load requirements:

  • 140kVA import capacity

  • Ground Source Heat Pump (~38kW)

  • 2 passenger lifts

  • 3 dual EV charging units (7.3kW per outlet)

  • Full building services including kitchen, laundry, and medical support systems

This load profile required careful consideration of:

  • Peak demand and diversity

  • Future-proofing the connection

  • Network constraints and capacity availability

The Challenge

This project presented several overlapping risks:

  • A constrained site on a busy A-road junction

  • Multiple site layout changes impacting utility infrastructure

  • Limited availability of temporary electrical capacity

  • Requirement to disconnect existing gas and electricity supplies

  • Commercial pressure around an expiring water quotation

Without early coordination, these factors had the potential to delay the programme and increase costs.

Our Approach

We were engaged early to provide a strategic overview of utility requirements, allowing us to:

  • Assess LV vs HV connection options based on a detailed load profile

  • Coordinate evolving substation and meter positions with the design team

  • Manage multiple stakeholders: DNO, ICP, IDNO, and water authority

  • Develop a phased utility strategy to support the construction programme

Our role focused on actively managing risk, rather than reacting to issues as they arose.

Why This Matters for Care Home Developers

Modern care home developments are placing increasing demand on utility infrastructure due to:

  • Electrification of heating (heat pumps)

  • EV charging requirements

  • 24/7 operational demand

Even relatively standard schemes are now approaching the LV to HV tipping point.

Early engagement ensures:

  • The right connection strategy is selected

  • Risks are identified and managed early

  • Programme and cost certainty are maintained

Key Challenges & Solutions

HV Connection Redesigns

The HV solution required three redesigns due to changing site layouts.
We worked closely with network stakeholders to adapt the design without restarting the process.

Temporary Power Constraints

The available LV temporary supply provided only partial capacity.
We:

  • Allocated supply to the tower crane only

  • Avoided overloading the network

  • Reduced reliance on generators

Complex Cable Routing

The site’s location required careful planning of offsite works.
Early coordination of traffic management and permits avoided delays.

Existing Utility Disconnections

We managed the disconnection of legacy gas and electricity supplies following demolition of the existing building.

Renewable Integration (G99)

The scheme included 140kW of solar PV, requiring G99 approval.
We coordinated the process to ensure compliance and timely approval.

Water Strategy & Commercial Negotiation

  • Existing water supply used as a temporary build supply

  • Successfully negotiated with Severn Trent to extend an expired quotation, avoiding delays and additional costs

Delivery Model

  • ICP appointed for contestable works

  • IDNO adoption secured, providing programme control and long-term value

The Outcome

Despite multiple design changes and site constraints:

  • Utility works were delivered in line with programme

  • Temporary power was managed efficiently without excessive cost

  • Renewable generation was successfully integrated

  • Commercial risks were mitigated

The client benefited from a coordinated and adaptable utility strategy, ensuring the development progressed without unnecessary delays.

Client Comment

“Knowing that all elements of the offsite works are handled professionally and efficiently is a big thing for us as a company. The communication and delivery from Shadwick UC is always excellent – even on tricky jobs such as Hatton.”

Jess Thorpe – LNT Construction